一、根据滑触线现场情况,本文就DMHX-200A-L滑触线为例,滑触线采购好后,根据厂家提供的说明说,进行安装。先将角钢支架按照1.25米的距离焊接或者固定在行车轨道压板底下。
A sliding contact line, according to the situation of field, in this paper, DMHX-200A-L sliding contact line as an example, the sliding contact line buy good, according to the instructions provided by the manufacturers say, installation. The first angle bracket according to the distance of 1.25 meters of welding or fixed on the lane rail clips underneath.
二、固定好角钢支架后,在角钢支架下面安装好提挂架和固定架。
Two, fixed angle steel bracket, installed and fixed in the frame of the rack angle provided below the bracket.
三、之后再将行车滑触线固定在提挂架和固定架之下,并安装好动力输入,各滑触线连接点的铝接头,之后安装接头护套和端冒。
Three, then driving sliding contact line is fixed on the rack and a fixing bracket provided below, and installed power input, aluminum joint of each sliding contact line connection point, after the installation of the sheath and the end joint at.
四、集电器安装,将集电器支架焊接在行车的标准位置,将集电器穿入集电器支架上,并调整好集电器与行车滑触线的平行距离。
Four, electrical installation, the collector welding bracket in the standard location of traveling, the collector is penetrated into the collector on the bracket, and adjust the distance of parallel good collector and driving sliding contact line.
行车滑触线调试。各项设备安装好后,要进行滑线调试准备。用设备保持好角钢支架的平行,各滑线不弯曲。之后,通电测试行车运行。
Crane sliding contact line commissioning. The equipment after installation, must carry on the slip line debugging preparation. Using the special equipment to maintain a good angle bracket in parallel, each slide line does not bend. After the power on test running.